Wednesday, September 9, 2015

Material Calculation for Concrete Mixing Designs

Introduction to Concrete

Concrete is an artificial stone which we used in construction. Concrete can be divided into two main categories as follows;

  1. Mass Concrete
  2. RCC Concrete
The only different between Mass concrete and RCC concrete is reinforcement. The mass concretes are designed without reinforcement while RCC concrete are designed with considerable reinforcement. The mass concrete are not being used as structural concrete. It is only used for leveling & as ground floor slabs and may be as some other architectural designs.

The concrete is basically made with cement, sand, metal and water to mix them together. The metal used for increasing the volume and also to give a considerable strength to the concrete. The sand used to fill the rest of the void which cannot be filled with metal. The cement is used in concrete will make these components attached well together with the jelly kind of thing that they produce in the mixing. Again the cement will make sure to fill other micro small voids which the sand cannot go through. 

Density of Cement  = 1440 kg/m3
Density of Sand      =  1920 kg/m3 
Density of Metal     = 1800 kg/m3


How to Find the cement, sand & metal quantities used in different type of  concrete mixing designs.
Calculations are based on the following assumption;
  • Sand includes 15% wastage
  • Cement Included 5% wastage
  • No wastage includes for metal
  • Contribution of the sand 65% per 1m3 of concrete by volume
  • Contribution of metal 85%  per 1m3 of concrete by volume
  • Contribution of cement 2% per 1m3 of concrete by volume
Nominal Mixing Designs
  1. G15 (C:S:M = 1:3:6)
  2. G20 (C:S:M = 1:2:4)
  3. G25 (C:S:M = 1:1 1/2:3)
  4. G30 (C:S:M = 1:1:2)

Contribution of material for 1 m3 of concrete = Sand 65% + Metal 85% + Cement 2%
                                                                          = 152 %
                                                                          = 1.52 m3

This means (1.52m3) to produce a 1m3 of solid concrete requires a 1.52 m3 of the actual quantity of the above material.

Hence, we can find the required material for the different type of concrete.

Required Material for G15 Concrete

1. G15 (C:S:M = 1:3:6)

Cement  = 1/10 = 0.1
Sand      = 3/10 = 0.3
Metal     = 6/10 = 0.6

Number of 50 kg cement bags per 1m3 = 0.1 x 1.52 m3 / Volume of cement bag
                                                             = 0.152 / 0.035
                                                             = 4.343 
                                                             = 4.343 x 1.05 
                                                             = 4.560 Nr

Therefore required number of cement bags per 1Cu = 4.56 x 2.83 Nr
                                                                                   = 12.91 Bags
                                                    Say Nr of Bags      = 13 Nos

 Required amount of Sand = 0.3 x 1.52 Cu 
                                           = 0.456 Cu
                                           = 0.456 x 1.15 Cu
                                           = 0.525 Cu

Say Required Amount of Sand      = 0.53 Cu


 Required amount of Metal = 0.6 x 1.52 Cu 
                                            = 0.912 Cu

Say Required Amount of Metal      = 0.91 Cu


Required material for G20 Concrete

2. G20 (C:S:M = 1:2:4)

Cement  = 1/7 = 0.14
Sand      = 2/7 = 0.29
Metal     = 4/7 = 0.57

Number of 50 kg cement bags per 1m3 = 0.14 x 1.52 m3 / Volume of cement bag
                                                             = 0.21 / 0.035
                                                             = 6.00 
                                                             = 6.00 x 1.05 
                                                             = 6.30 Nr

Therefore required number of cement bags per 1Cu = 6.30 x 2.83 Nr
                                                                                   = 17.83 Bags
                                                    Say Nr of Bags      = 18 Nos

 Required amount of Sand = 0.28 x 1.52 Cu 
                                           = 0.43 Cu
                                           = 0.43 x 1.15 Cu
                                           = 0.50 Cu

Say Required Amount of Sand      = 0.50 Cu


 Required amount of Metal = 0.571 x 1.52 Cu 
                                            = 0.87 Cu

Say Required Amount of Metal      = 0.87 Cu


Required material for G25 Concrete

3. G25 (C:S:M = 1:1.5:3)

Cement  = 1/5.5 = 0.18
Sand      = 1.5/5.5 = 0.27
Metal     = 3/5.5 = 0.55

Number of 50 kg cement bags per 1m3 = 0.18 x 1.52 m3 / Volume of cement bag
                                                             = 0.27 / 0.035
                                                             = 7.71 
                                                             = 7.71 x 1.05 
                                                             = 8.1 Nr

Therefore required number of cement bags per 1Cu = 8.1 x 2.83 Nr
                                                                                   = 22.92 Bags
                                                    Say Nr of Bags      = 23 Nos

 Required amount of Sand = 0.27 x 1.52 Cu 
                                           = 0.41 Cu
                                           = 0.41 x 1.15 Cu
                                           = 0.47 Cu

Say Required Amount of Sand      = 0.47 Cu


 Required amount of Metal = 0.55 x 1.52 Cu 
                                            = 0.836 Cu

Say Required Amount of Metal      = 0.87 Cu


Required material for G30 Concrete

4. G30 (C:S:M = 1:1:2)

Cement  = 1/4 = 0.25
Sand      = 1/4 = 0.25
Metal     = 3/5.5 = 0.50

Number of 50 kg cement bags per 1m3 = 0.25 x 1.52 m3 / Volume of cement bag
                                                             = 0.38 / 0.035
                                                             = 10.86 
                                                             = 10.86 x 1.05 
                                                             = 11.40 Nr

Therefore required number of cement bags per 1Cu = 11.40 x 2.83 Nr
                                                                                   = 32.26 Bags
                                                    Say Nr of Bags      = 31 Nos

 Required amount of Sand = 0.25 x 1.52 Cu 
                                           = 0.38 Cu
                                           = 0.38 x 1.15 Cu
                                           = 0.437 Cu

Say Required Amount of Sand      = 0.44 Cu


 Required amount of Metal = 0.50 x 1.52 Cu 
                                            = 0.76 Cu

Say Required Amount of Metal      = 0.76 Cu

Please go through the below link to survey form.

https://docs.google.com/forms/d/e/1FAIpQLSfEaESLCOB1f1RjUpi0QpBp_bAKKhLTgqcqLlBaFSZm5ITH1A/viewform?c=0&w=1&usp=mail_form_link

22 comments:

  1. How do we get , coefficient 1.05 of cement, 1.15 of sand and 1.52 of Metal?

    ReplyDelete
  2. 1.05,1.15 must be adding safety margin for wastage.1.52 given in top of calculation procedure.

    ReplyDelete
  3. I have doubt about ur calculations... u mentioned
    Number of 50 kg cement bags per 1m3 = 0.25 x 1.52 m3
    Required amount of Sand = 0.25 x 1.52 Cu
    When we calculate the cement bags, u multiply by 1.52m3 same as calculate the cement&metal u directly multiply 1.52cu. Is it correct?
    (1cube=2.83m3) can you tell solution?

    ReplyDelete
  4. This comment has been removed by the author.

    ReplyDelete
  5. Therefore required number of cement bags per 1Cu = 11.40 x 2.83 Nr

    May i know how do you get the 2.83 Nr ?

    ReplyDelete
  6. Very well done. Absolutely brilliant information. I'm in love with this blog. they always provide such a great information. sand and cement mix

    ReplyDelete
  7. This comment has been removed by the author.

    ReplyDelete
  8. Thanks for sharing. Great post very Informative. Tree trimming is important for aesthetic reasons and to encourage the growth of strong, healthy trees Thanks for posting this again. .Concrete Pumps Hire In London

    ReplyDelete
  9. Thanks for sharing. Great post very Informative. What a great article you've written! This is useful and well-thought out information with though.t-provoking viewpoints and content. I'm impressed with how well you have presented this information in such and interesting and original way. Thanks for posting this again. .Mix On Site Concrete In London

    ReplyDelete
  10. Looking forward to reading more. Great article. Really thank you!ready mix concrete Los Angeles

    ReplyDelete
  11. Wow i can say that this is another great article as expected of this blog.Bookmarked this site.. Rectify

    ReplyDelete
  12. This comment has been removed by the author.

    ReplyDelete
  13. This comment has been removed by the author.

    ReplyDelete
  14. If you are new to working with concrete then you probably are not aware of the mistakes that novice concrete workers often make. This article is designed to help beginners understand what to do and what not to do when working with concrete. Learn the basics of concrete mixing, the importance of water content in the mix, and how to avoid compromising the strength of the concrete you are using. More Info

    ReplyDelete
  15. How i get a total cement volume of any of grade which included reinforcement alrady ?

    ReplyDelete
  16. Thank you so much as you have been willing to share information with us. We will forever admire all you have done here because you have made my work as easy as ABC. dark0de market url

    ReplyDelete
  17. Thanks For sharing this Superb article.I use this Article to show my assignment in college.it is useful For me Great Work. dark0de market link

    ReplyDelete
  18. This article is brimming with information about concrete mixing for more like this. I have additionally discovered an article anybody can check for more data Concrete Mixer , It was knowingly more instructive. You may discover more insights regarding it here

    ReplyDelete
  19. Hi to everybody, here everyone is sharing such knowledge, so it’s fastidious to see this site, and I used to visit this blog daily Concrete cancer

    ReplyDelete
  20. Overlook any insights about the expense until you get the full picture so you remember the significant viewpoints to search for. concrete contractor columbia mo

    ReplyDelete
  21. Nice Blog! Very Insightful on concrete.
    concrete

    ReplyDelete
  22. This comment has been removed by the author.

    ReplyDelete

Rate analysis for brickwork in construction

When we analyse a rate for construction work, we can get different answers according the previous records which have been recorded during c...