Calculation of material and labour requirement for rubble masonry incement mortar 1:5 in foundation

Random Rubble Masonry in Cement mortar 1:5 in foundation (1Cu)

Description
Unit
Quantity
6”-9” Rubble
Cu
1.3
Cement (50kg bags)
Nr
5
Sand
Cu
0.3
Water
Gal
100
Mason
Day
1
Unskilled labourer
Day
3
Total



Generally, to construct a rubble foundation, the materials required are rubble, cement, sand, and water. Mixing of cement and sand mortar ratio can be changed depending on the strength should obtain but the most frequently used ratio is 1:5 (cement:sand) mix, which we are going to discuss in this article.

In the above table, material and labour requirement for 1 Cube of rubble masonry work have been indicated based on the field experience and building schedules of rates. In this calculation, it is necessary to add 5-10% of wastage for sand. 

Ex:- Assume we have to construct a rubble foundation, which is 450mm in width, 600mm in height and which is 50m long. Assume water is available at the site. What are the material and amount of each material are we going to purchase to get the work done.

First, we need to calculate the total actual volume of rubble work.

 V = 0.45m x 0.6m x 50m
     = 13.5 m3
     = 4.77 cube 

According to table given,

Rubble = 4.77 x 1.3 Cube
             = 6.20 Cube

Cement = 4.77 x 5 Bags (50kg)
              = 23.85 Bags
              = 24 Bags

Sand = 4.77 x 0.3 Cube
         = 1.43 Cube

Add wastage 5% = 1.43 x 5%
                            = 0.07 Cube

Total Sand Requirement = 1.50 Cube

Therefore your Purchasing order should be;

Rubble = 6.20 Cu
Cement = 24 bags (50kg)
Sand = 1.50 Cu

Note: When we issue the payments for the labours, consider only the actual volume of rubble masonry and not the amount of purchasing of rubble.

Therefore, payment should be issued for labour for this work is 4.77 cu (Skilled labour days 4.77 and  unskilled labour days 14.31). 

Note: 1cube = 100 cu.ft = 2.83 cum


Typical Rubble Foundation Detail















Check Out the Rubble Masonry Calculator




31 comments:

  1. can you provide ratio of rubble to cement and sand

    ReplyDelete
  2. Thanks for sharing, very clear.

    ReplyDelete
  3. Thanks for sharing, very clear.

    ReplyDelete
  4. Calculation of material and labour requirement for rubble masonry incement mortar 1:6 in foundation

    ReplyDelete
  5. Hi, The CM ratio is given as 1:5. However 5 bags of cement and 0.3cum of sand has a different ratio which is richer than 1:5. Am i missing something here? Please clarify. Thanks

    ReplyDelete
    Replies
    1. That is for 1 cu which means 2.83 cum. Volume of 50kg cement bag is 0.035 m3. For 5 bags 5×0.035 m3 = 0.175m3 or 0.06 cu. Thus, cement (0.06) :sand (0.3) = 1:5

      Delete
  6. i need sssm calculation for the following details
    Length-164.60m
    Width-450mm
    Height-1350mm and we are using 1:4CM Please clarify with all the details

    ReplyDelete
  7. This comment has been removed by the author.

    ReplyDelete
  8. What is the factor of 1.3 in rubble calculation?

    ReplyDelete
  9. Replies
    1. change those amount to imperial unit,
      therefore; 600mm=2ft, 450mm=1.5ft, and 50m=50*3.281= 164.05ft
      v= 2*1.5*164.05 = 492.15/100 which is 4.92cube

      Delete
    2. NOW I GET IT,WHERE 4.77 FROM
      V: 0.45M*0.60M*50M = 13.5M3
      NOTE. 1Cu.Ft = 2.83M3

      HOW TO GET 1CU = 13.5/2.83 = 4.77CU.FT

      Delete
  10. Please clarify where you get this value 4.77

    ReplyDelete
  11. Hello for everyone, i am still not understand about the material calculation for R/R Stone masonry(1:5 csm) in 4.77m3 Quantity, please let me clarify now.

    ReplyDelete
  12. 24 cement bags for 1.5 cube of sand its different what is the cement sand motar ratio?

    ReplyDelete
  13. Thanks for sharing. This is very clear

    ReplyDelete
  14. A good masonry contractor will guarantee his work, so you have some insurance that the finished product will last. Masonry contractors Columbus Oh A good contractor should also understand any nearby, state, and federal regulations that will affect the materials getting used or the project being performed, in order that you may be assured any work is compliant with government laws.

    ReplyDelete
  15. We are your local Concreters, with over 25 years of experience in Kerbing, Slabs & Driveways. We are committed to quality workmanship & excellence in the best customer service on every job. We have a team of experienced concrete contractors in Newcastle and Central Coast, who is dedicated to getting the accurate surfacing solution to modify the appearance of your property and enhance its driveways appeal.

    ReplyDelete
  16. The article was up to the point and described the information about education and learning. Thanks to blog author for wonderful and informative post. tellthebell.com

    ReplyDelete

  17. Thanks for taking the time to discuss this, I feel strongly love and read more on this topic. If possible, such as gain knowledge, would you mind updating your blog with additional information? It is very useful for me.


    krogerfeedback.com

    ReplyDelete
  18. clearly explained but a small doubt how you have considered 24 bags for 4.77 cube volume is it a thumb rule or something please reply other than that its self explainatory.

    ReplyDelete
  19. Tellthebell A well-known unsavoury provider federating in the US, Taco Ringer, is the leader of the Tellthebell consumer loyalty poll. For more info https://etellthebell.shop/

    ReplyDelete
  20. By completing the Acme Markets survey, you have the chance to win a $100 Gift Card. To take part in the Acme employee survey and Acme supermarkets survey, you are not required to make a purchase. https://acmemarketssurveyus.shop/

    ReplyDelete

Rate analysis for brickwork in construction

When we analyse a rate for construction work, we can get different answers according the previous records which have been recorded during c...