Random Rubble Masonry in Cement mortar 1:5 in foundation (1Cu)
Description
|
Unit
|
Quantity
|
6”-9” Rubble
|
Cu
|
1.3
|
Cement (50kg bags)
|
Nr
|
5
|
Sand
|
Cu
|
0.3
|
Water
|
Gal
|
100
|
Mason
|
Day
|
1
|
Unskilled labourer
|
Day
|
3
|
Total
|
Generally, to construct a rubble foundation, the materials required are rubble, cement, sand, and water. Mixing of cement and sand mortar ratio can be changed depending on the strength should obtain but the most frequently used ratio is 1:5 (cement:sand) mix, which we are going to discuss in this article.
In the above table, material and labour requirement for 1 Cube of rubble masonry work have been indicated based on the field experience and building schedules of rates. In this calculation, it is necessary to add 5-10% of wastage for sand.
Ex:- Assume we have to construct a rubble foundation, which is 450mm in width, 600mm in height and which is 50m long. Assume water is available at the site. What are the material and amount of each material are we going to purchase to get the work done.
First, we need to calculate the total actual volume of rubble work.
V = 0.45m x 0.6m x 50m
= 13.5 m3
= 4.77 cube
According to table given,
Rubble = 4.77 x 1.3 Cube
= 6.20 Cube
Cement = 4.77 x 5 Bags (50kg)
= 23.85 Bags
= 24 Bags
Sand = 4.77 x 0.3 Cube
= 1.43 Cube
In the above table, material and labour requirement for 1 Cube of rubble masonry work have been indicated based on the field experience and building schedules of rates. In this calculation, it is necessary to add 5-10% of wastage for sand.
Ex:- Assume we have to construct a rubble foundation, which is 450mm in width, 600mm in height and which is 50m long. Assume water is available at the site. What are the material and amount of each material are we going to purchase to get the work done.
First, we need to calculate the total actual volume of rubble work.
V = 0.45m x 0.6m x 50m
= 13.5 m3
= 4.77 cube
According to table given,
Rubble = 4.77 x 1.3 Cube
= 6.20 Cube
Cement = 4.77 x 5 Bags (50kg)
= 23.85 Bags
= 24 Bags
Sand = 4.77 x 0.3 Cube
= 1.43 Cube
Add wastage 5% = 1.43 x 5%
= 0.07 Cube
Total Sand Requirement = 1.50 Cube
Therefore your Purchasing order should be;
Rubble = 6.20 Cu
Cement = 24 bags (50kg)
Sand = 1.50 Cu
Note: When we issue the payments for the labours, consider only the actual volume of rubble masonry and not the amount of purchasing of rubble.
Therefore, payment should be issued for labour for this work is 4.77 cu (Skilled labour days 4.77 and unskilled labour days 14.31).
Note: 1cube = 100 cu.ft = 2.83 cum
can you provide ratio of rubble to cement and sand
ReplyDeleteThanks for sharing, very clear.
ReplyDeleteThanks for sharing, very clear.
ReplyDeleteCalculation of material and labour requirement for rubble masonry incement mortar 1:6 in foundation
ReplyDeleteHi, The CM ratio is given as 1:5. However 5 bags of cement and 0.3cum of sand has a different ratio which is richer than 1:5. Am i missing something here? Please clarify. Thanks
ReplyDeleteThat is for 1 cu which means 2.83 cum. Volume of 50kg cement bag is 0.035 m3. For 5 bags 5×0.035 m3 = 0.175m3 or 0.06 cu. Thus, cement (0.06) :sand (0.3) = 1:5
Deletei need sssm calculation for the following details
ReplyDeleteLength-164.60m
Width-450mm
Height-1350mm and we are using 1:4CM Please clarify with all the details
I need calculate
DeleteThis comment has been removed by the author.
ReplyDeleteWhat is the factor of 1.3 in rubble calculation?
ReplyDeleteHow u get 4.77 value?
ReplyDeleteNote: 1cube = 100 cu.ft = 2.83 cum
Deletechange those amount to imperial unit,
Deletetherefore; 600mm=2ft, 450mm=1.5ft, and 50m=50*3.281= 164.05ft
v= 2*1.5*164.05 = 492.15/100 which is 4.92cube
NOW I GET IT,WHERE 4.77 FROM
DeleteV: 0.45M*0.60M*50M = 13.5M3
NOTE. 1Cu.Ft = 2.83M3
HOW TO GET 1CU = 13.5/2.83 = 4.77CU.FT
4.77 how u get the value
ReplyDeletePlease read the example and assumptions... tks!
DeleteVery useful thanku
ReplyDeletePlease clarify where you get this value 4.77
ReplyDeleteHello for everyone, i am still not understand about the material calculation for R/R Stone masonry(1:5 csm) in 4.77m3 Quantity, please let me clarify now.
ReplyDelete24 cement bags for 1.5 cube of sand its different what is the cement sand motar ratio?
ReplyDeleteThanks for sharing. This is very clear
ReplyDeleteThank you very much
ReplyDeleteA good masonry contractor will guarantee his work, so you have some insurance that the finished product will last. Masonry contractors Columbus Oh A good contractor should also understand any nearby, state, and federal regulations that will affect the materials getting used or the project being performed, in order that you may be assured any work is compliant with government laws.
ReplyDeleteThank you.
ReplyDeleteWe are your local Concreters, with over 25 years of experience in Kerbing, Slabs & Driveways. We are committed to quality workmanship & excellence in the best customer service on every job. We have a team of experienced concrete contractors in Newcastle and Central Coast, who is dedicated to getting the accurate surfacing solution to modify the appearance of your property and enhance its driveways appeal.
ReplyDeleteThe article was up to the point and described the information about education and learning. Thanks to blog author for wonderful and informative post. tellthebell.com
ReplyDelete
ReplyDeleteThanks for taking the time to discuss this, I feel strongly love and read more on this topic. If possible, such as gain knowledge, would you mind updating your blog with additional information? It is very useful for me.
krogerfeedback.com
clearly explained but a small doubt how you have considered 24 bags for 4.77 cube volume is it a thumb rule or something please reply other than that its self explainatory.
ReplyDeleteDRHZDRX
ReplyDeleteTellthebell A well-known unsavoury provider federating in the US, Taco Ringer, is the leader of the Tellthebell consumer loyalty poll. For more info https://etellthebell.shop/
ReplyDeleteBy completing the Acme Markets survey, you have the chance to win a $100 Gift Card. To take part in the Acme employee survey and Acme supermarkets survey, you are not required to make a purchase. https://acmemarketssurveyus.shop/
ReplyDelete