Material and Labour Requirement for Precast Concrete Slab for 1Sqr (=100 Sqft)
- 1) 2”x2” welded mesh (12’x7’) = 1.2 Nr
- 2) 2” concrete topping (1:2:4), 1/4 chips = 0.17 Cu
- 3) Cement = 6.5 x 0.17 = 1.12 bags (50kg)
- 4) Sand = 0.5 x 0.17 = 0.09 Cu
- 5) Metal = 0.88 x 0.17 = 0.15 Cu
- 6) Floor beams Placing at 2’ c/c = 100 Lft
- 7) Masonry Soffit Blocks = 64 Nr
- 8) Labour charges & Transport charges can be changed
Since Quantities have been given now you will be able to
calculate the unit rate for the above work by inputting the material cost
depending on your area.
Note: Consider about the unit conversions otherwise the
calculations will go wrong.
1 Cu =
2.83 Cum
just what most individuals' desire. However, most of which have no idea of the inner thoughts and multi-step means of purchasing a fresh home concrete contractors midland tx
ReplyDeleteNice Blogs!
ReplyDeleteThanks for sharing this informative blog.
Concrete Supplies in Sydney is the second most consumed in the world after the consumption of water. Working as a market leader in the production of concrete, THE YARD offers a wide range of products and solutions. With an unparalleled history of product reliability, development and technical expertise of all products that are specifically designed for a wide variety of applications that includes the industrial, house building, agricultural and commercial applications. Our all products conform to credited quality assurance schemes and meet the standards.
The Yard Group!