Tuesday, September 16, 2014

Material and Labour requirement for mixing (1:1 1/2: 3) G25 concrete

Mixing Concrete 1:1 ½:3 (3/4”) G25

Description
Unit
Quantity
Cement (50 kg Bags)
Nr
23
Sand
Cu
0.42
¾” Metal
Cu
0.82
Hire of Mixer
Day
0.333
Water
Gal
150
Skilled labourer
Day
0.333
Unskilled labourer
Day
2
Total



With the given information in the above table you will be able calculate unit rate for mixing concrete (1:1 ½:3) G25 by in putting particular market rates for each material and labour in your area. Once you established the unit rate you can estimate the total cost of G25 concrete work in your building or house or whatever the construction by unit rate multiplying with total quantity of work.

Note: When you do you calculation consider about the units. (Cu,Cum,etc.)