Mixing Concrete
1:1 ½:3 (3/4”) G25
Description
|
Unit
|
Quantity
|
Cement (50 kg Bags)
|
Nr
|
23
|
Sand
|
Cu
|
0.42
|
¾” Metal
|
Cu
|
0.82
|
Hire of Mixer
|
Day
|
0.333
|
Water
|
Gal
|
150
|
Skilled labourer
|
Day
|
0.333
|
Unskilled labourer
|
Day
|
2
|
Total
|
With the given information in the above table you will be
able calculate unit rate for mixing concrete (1:1 ½:3) G25 by in putting
particular market rates for each material and labour in your area. Once you
established the unit rate you can estimate the total cost of G25 concrete work in
your building or house or whatever the construction by unit rate multiplying
with total quantity of work.
Note: When you do you
calculation consider about the units. (Cu,Cum,etc.)