Concrete Mixing Designs and Calculations for 1 Cu
Description
|
Unit
|
1:1 ½:3 (G25)
|
1:3:6 (G15)
|
1:2 ½:5
|
1:2:4 (G20)
|
1:1:3 (G30)
|
Quantity
|
Quantity
|
Quantity
|
Quantity
|
Quantity
|
||
Cement (50kg Bags)
|
Nr
|
23
|
13
|
14
|
18
|
31
|
Sand
|
Cu
|
0.47
|
0.53
|
0.6
|
0.5
|
0.44
|
Metal
|
Cu
|
0.82
|
0.92
|
0.9
|
0.88
|
0.76
|
Hire of Mixer
|
Day
|
0.333
|
0.333
|
0.333
|
0.333
|
0.333
|
Water
|
Gal
|
150
|
110
|
100
|
120
|
200
|
Skilled Labourer
|
Day
|
0.333
|
0.333
|
0.333
|
0.333
|
0.333
|
Unskilled Labourer
|
Day
|
2
|
2
|
2
|
2
|
2
|
Total for 1Cu of Concrete
|
There are different types of concrete we use in construction depend on the strength we need to achieve in the particular application. In order to meet the required strength of the structure, it is necessary to change the proportion of mixing of concrete elements (cement, sand, metal and water). The above table shows the commonly used concrete mixing designs in construction. It also provides the Labour and Material requirement for each mixing design. With the given data collection in the table, we should be able to calculate the required amount of the material, labor and plant for each mixing design.
Thanks!
ReplyDeleteYou are most welcome. Keep in touch !!!
DeleteInteresting simplification of the process. Nice job. Is the grade referred to cylinder strength or cube strength?
ReplyDeleteHello Mr. Lahiru Madusanka.
ReplyDeleteI found your blog very useful in knowing the basics of construction.
i want one one clarification. Im from India and the concrete calculator, sand price and metal price, i just want to know what units I must put. Whether it is for 1 cft of sand/metal ???