Saturday, August 29, 2015

Rate Analysis for Excavation Work

Excavation Cost & Rate

Rate analysis for excavation work is comparatively easy to establish because it does not require a material analysis. Therefore, we only have to consider the Labour and Equipment cost to determine the rate of excavation work. Generally excavation can be done by handheld tools such as hoes, shovels & etc. or using excavator machine. Depending on the work, we need to decide the method we should go with.

In this article, we are going to discuss the rate analysis for manual excavation using handheld tools. Assume we have to dig a pit for a particular column footing size of 900mm in width and 900mm in length and 1000mm in depth. First thing is we have to investigate the soil type of the site to determine what are the necessary tasks to be undertaken to complete the work properly. Such works can be as follows.

  • Shoring
  • Working Space
  • Dewatering
  • Rock required blasting

Assume we need a considerable working space of 150mm for each side to get the work done. Then, the practical excavation size of footing is 1200mm width & 1200mm length and 1000mm depth.

Actual excavation volume as per the drawings;

Volume (Actual) = 0.90 m x 0.90 m x 1.00 m
                      = 0.81 m3

Practical volume to be excavated is;

Volume (Practical) = 1.20 m x 1.20 m x 1.00 m
                      = 1.44 m3 

Assume that 0.50 days required to excavate 1m3 volume using one unskilled labourer. Say the rate for unskilled labourer per day is Rs.1,500.

Therefore, the labour cost of excavation for the given work is;

Labour Cost = 1.44 m3 x (0.50 days / 1m3) x (Rs. 1,500 / 1day)
                     = Rs.1,080

Assume Tools & Equipment Cost = 5% of Labour Cost
                                                       = 0.05 x Rs.1,080
                                                       = Rs.54

Total Basic Cost = Labour Cost + Tools & Equipment Cost
                           = Rs.1,080 + Rs.54
                           = Rs.1,134

Now let's add Overheads & Profit 20%

Therefore, Total with OH & P 20% = Rs.1,134 /(100%/(100%-20%)
                                                          = Rs.1,292.50


After calculating the total cost with OH & P, we have to find the rate for excavation work. In this step, we need to be very careful enough that the total to be divided by the actual volume which is according to drawings. (Should refer the preamble notes in the tender)

Rate for Excavation Work per 1m3 = (Total with OH & P) / Volume (Actual)

                                                         = Rs.1,292.50 / 0.81m3

                                                         = Rs.1595.68/m3




3 comments:

  1. When choosing general contractors for your home remodel project, you should put a lot of time and careful thinking into the selection process.
    For more information: excavation massachusetts

    ReplyDelete
  2. In Massachusetts, the most common species of termites swarm on a warm day after a rainfall. Swarms may occur during the winter in heated buildings.excavation massachusetts

    ReplyDelete
  3. You already know the fact that every business in this world requires seed capital and excavation services Toronto are no exceptions. But it is not only about getting
    the initial capital.See more at-excavation massachusetts

    ReplyDelete

Rate analysis for brickwork in construction

When we analyse a rate for construction work, we can get different answers according the previous records which have been recorded during c...